Factory building large modules for new nukes unable to produce on schedule, set to close

Fox Business News reported today:

The U.S. nuclear industry has started building its first new plants in decades using prefabricated Lego-like blocks meant to save time and money.

So far, it’s not working.

Quality and cost problems have cropped up again, raising questions about whether nuclear power will ever be able to compete with other electricity sources.

The first two reactors being built in 18 years, Southern Co.’s Vogtle plant in Georgia and SCANA Corp.’s VC Summer plant in South Carolina, are being assembled in large modules. Large chunks of those modules are built off-site to improve quality and avoid cost overruns.

However, a factory in Louisiana struggled to produce the parts on schedule. Now that factory is being phased out and new manufacturers are being brought in.

 

Advertisements

About Robert Singleton

By day, I work for a call center. In my spare time, I try to save my hometown (and planet) from a nearly constant onslaught of greedheads, lunatics and land developers. I live in a fictional town called Austin, Texas, where I go to way too many meetings.
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s